| Client / Location | Nature of Work | Value |
| WMC Resources | ||
|
Olympic Dam SA
|
25 ventilation shafts, including 646m x 4.5m vent shaft 614m x 4.5m vent shaft |
$1.5 Million $1.4 Million |
|
Lancefield WA
|
390m x 4.1m vent shaft | $1.0 Million |
|
Leinster WA
|
6 x 90m x 4m horizontal drives | $1.0 Million |
|
Kambalda WA
|
530m x 3.1m shaft | $1.4 Million |
|
Pasminco Mining
|
||
| Broken Hill NSW | 588m x 4.1m shaft | $2.1 Million |
| 820m x 1.8m shaft | $1.4 Million | |
| Rosebery, Tas | 650m x 4.5m shaft, inc
38m lined pre-sink |
$3.0 Million |
|
Normandy Mining
|
||
| Scuddles WA | 350m x 4.1m shaft | $1.0 Million |
| Callie NT | 300m x 4.5m shaft inc. strip and line from 1.8m drilled shaft for top 112m. | $2.2 Million |
|
Ulan Coal Mines
|
||
| Ulan, NSW | 180m x 5.0m shaft fully concrete lined with a 47m pre-sink. | $2.2 Million |
|
Renison Goldfields
|
||
| Henty Tas | 377m x 3.0m underground shaft. | $1.0 million |
|
Capricorn Coal Management
|
||
| German Creek, Qld | Two 200m x 4.8m shafts, inc. ground support and lining. |
$2.6 million |
|
Springvale Colliery
|
||
| Lithgow, NSW | Two 140m x 4m shafts fully concrete lined. | $2.5 million |
| Northside Storage Tunnel Alliance | ||
| Sydney NSW | 154m x 5m shaft | $1.0 million |
| Homestake Australia | ||
| Darlot, WA | 355m x 3.8m shaft, inc. 70m deep lined pre-sink and installation of ground support. | $2.8 million |
| Rio Tinto | ||
| Cobar, NSW | 900m x 3.1m shaft 900m x 4.0m shaft |
$3.2 million |